Work Name
|
(1207009031/WC/1000021638) Digging of new Pond (91/1/2) |
Nature of Work |
Water Conservation
|
|
On Going
|
Scope of Work
|
Start Status |
End Status |
Existing |
Renovtion of Community Ponds for Comm |
|
Location
|
Start Location |
KURAR IBRAHIMPUR |
Khata No. |
Plot No. |
|
|
|
Sanction No. and Sanction Date
: 1207012/2021-2022/14420/AS ,
30/07/2021
|
Whether Included in Five Year Perspective Plan
: Yes |
Whether Work Approved in Annual Plan
: Yes |
Estimated Cost (In Lakhs)
:
16.53302
|
Estimated Completion Time (in Months)
|
4 |
Expenditure Incurred (in Rs.)
|
Unskilled |
Semi-Skilled |
Skilled |
Material |
Contingency |
Total |
898945 |
0 |
19159 |
425044 |
0 |
1343148 |
|
Employment Generated
|
Pesrondays |
Total No. of Persons Given Work |
Unskilled |
2897 |
326 |
Semi-Skilled |
0 |
0 |
|
0 |
0 |
|
Distinct Number of Muster Rolls used(Amount)
|
517(85680),556(141435),612(53865),634(59850),635(110250), 637(22680),638(1890),231(44354),232(32438),241(3641), 309(17543),366(29459),367(33100),368(23170),369(23501), 421(20839),422(11908),423(28396),424(11679),426(2977), 427(4580),728(42037),729(30783),730(37403),731(8275), 732(8606),734(4303),747(4303),
|
Work start date |
02/12/2021 |
Photo Uploaded of Work
|
Before Start of Work(Work Site)
|
During Execution of Works
|
|
|
|